Project Futurus
Week 3 Wednesday (Lab1)
- Preliminary ideas
- Individual’s SRS
- Individual’s reading
Week 4 Wednesday
- Combine, refine and finalize SRS
- Draft Use Case Diagram
- Individual works on Analyze and model(A&M) system specifications
- 2 people finalize Use Case Diagram done by Friday(as well as A&M)
- Appoint 2 individuals to database design, start to think about database
- Appoint 2 individuals to user interface design, start to think about UI design
- Individual’s reading
Week 4 Weekends
- Submit Project schedule, SRS, use-case diagram
- Combine, refine A&M system specifications
- 2 people start on database draft design
- 2 people start on user interface draft design
- Individual’s reading
Week 5 Wednesday (Lab2)
- Finalize Analyze and model system specifications
- Prototyping frontend
- Prototyping backend
Week 5 Weekends
- Progress check, reschedule if necessary
- Submit Analyze and model system specifications
- Prototyping frontend
- Prototyping backend
Week 6 Wednesday
- Progress check, reschedule if necessary
- Review system requirement
- Prototyping frontend.
- Prototyping backend.
- Form frontend development team
- Form backend development team
- Detailed frontend UI design
- Detailed backend logical design
Week 6 Weekends
- Progress check, reschedule if necessary
- Review system requirement
- Finalize Prototyping frontend.
- Finalize Prototyping backend.
- Integrate Detailed frontend UI design to prototype
- Integrate Detailed backend logical design to prototype
- Implement major functionalities
Week 7 Wednesday (Lab 3)
- Progress check, reschedule if necessary
- Review system requirement
- Implement major functionalities
Week 8 (CIDP)
- Daily progress check, reschedule if necessary
- Fully implement system.
- Review system requirement when necessary
Week 9 Wednesday (Lab 4)
- Progress check, reschedule if necessary
- Finalize implementation
- Integrate frontend and backend
Week 9 Weekends
- Finalize project
- Self project evaluation
Week 11 Wednesday (Lab 5)
- Demo and evaluation