Current Project

Project Name: Futurus [Latin futurus "going to be", the etymon of English word ”Future”]

Project Slogan: Futurus, the future of humanitarian movement.

Project Topic: A Volunteer Teachers Network Portal System

Wednesday, April 7, 2010

Final Report by Team creatiNno sTUdio

Final Report
by Team creatiNno sTUdio

ACKNOWLEDGEMENT
The motivation driving our team, CreatiNno sTUdio, is to provide an online platform for sharing and acquiring educational resources. With this goal in mind, the website, ‘Futurus’ has been designed, after months of brainstorming, planning and development.

We wish to express gratitude to our lecturer Wong Ee Kian and Assistant Professor Malcolm Low for imparting us knowledge of the subject which was very useful in doing this project and Lab Supervisor Zhang Jie for his invaluable support and guidance. Last but not the least; we would like to thank the lab technicians for resolving our difficulties during lab session. This project would not have been possible without the constant support of all the above mentioned people.

Team CreatiNno sTUdio
 
Full report is available at following link:
https://docs.google.com/fileview?id=0B50DB3EHd3ULOTRkOGIzNWEtMmFhZC00NWUwLTlkZTUtODNiMmYwMmFhZmQw&hl=en


[+]

Tuesday, March 30, 2010

Testing

Testing Function:
Authenticate.authentication. register(User user)

Subprogram:
Authenticate.authentication. checkEmail(String email)
Authenticate.authentication. checkPassword(String password)

Whitebox Testing:
Detailed testing documentation is available at following link:
http://docs.google.com/fileview?id=0B50DB3EHd3ULMTNmNjcxMzYtZWQ0MS00ODYzLWE3NGQtY2IyZTVkYWVhMzQ3&hl=en


Blackbox Testing:
Detailed testing documentation is available at following link:


[+]

Tuesday, February 23, 2010

Public Review Folder Update

Update item: Software Requirements Specification, SRS V2.0.3 
  • Refinement of SRS User Interface Requirements
Check out the update at http://docs.google.com/leaf?id=0B50DB3EHd3ULYTQ3ZjA1YmQtOTI3NC00NDA0LWFkY2ItZjZhOTE5N2EzNzVl


[+]

Class Diagram and Sequence Diagram

Class Diagram and Sequence Diagram
Class Diagram

Sequence Diagram
Accessing Website

Footprints

Login and Logout

User Features

These diagrams are also available at Public Review Folder http://docs.google.com/leaf?id=0B50DB3EHd3ULYTQ3ZjA1YmQtOTI3NC00NDA0LWFkY2ItZjZhOTE5N2EzNzVl


[+]

Wednesday, February 17, 2010

Entity-Relationship Diagram

ERD V1 is released. This is a preliminary design.

 
  
  
 




[+]

Wednesday, February 10, 2010

Public Review Folder Update

Update item: Software Requirements Specification, SRS V2.0.1
  • Refinement of SRS Product Vision
  • Refinement of SRS Business Requirements
Check out the update at http://docs.google.com/leaf?id=0B50DB3EHd3ULYTQ3ZjA1YmQtOTI3NC00NDA0LWFkY2ItZjZhOTE5N2EzNzVl

[+]

Tuesday, February 9, 2010

Public Review Folder Update

Update item: Software Requirements Specification, SRS V2
  • Added Domain Dictionary
Check out the update at http://docs.google.com/leaf?id=0B50DB3EHd3ULYTQ3ZjA1YmQtOTI3NC00NDA0LWFkY2ItZjZhOTE5N2EzNzVl

[+]

Imagine Cup 2010


You can find the local Software Design competition rules here -http://www.imaginecup.com.sg/rules.aspx

For all other categories and awards the timelines are on the official website – http://imaginecup.com/Default.aspx

For the local software design rounds, you need to submit a proposal document by 9th March, only if you make it to top 16 which you will know by mid-march, you need to start building your app and have it ready by 17th May.

Let me know if you are interested.

[+]

Public Review Folder Update

Update item: Software Requirements Specification, SRS V2

  1. Refined Product Description
  2. Refined Functional Requirements
  3. Added Use Case Diagram
  4. Added Use Case Description

Public Review Folder

Visit our Public Review Folder at Google docs.

Our Public Review Folder contains
  • CSC207/CIDP Schedule.
  • CSC207/CIDP Project Specification Draft
  • CSC207/CIDP Team Contact Information
  • CSC207/CIDP Team FreeSlotsTimetable
  • CSC207/CIDP Preliminary Ideas
  • CSC207/CIDP Software Requirements Specification
 [+]

Friday, February 5, 2010

Project Futurus Schedule

Project Futurus

Week 3 Wednesday (Lab1)
  • Preliminary ideas
  • Individual’s SRS
  • Individual’s reading

Week 4 Wednesday
  • Combine, refine and finalize SRS
  • Draft Use Case Diagram
  • Individual works on Analyze and model(A&M) system specifications
  • 2 people finalize Use Case Diagram done by Friday(as well as A&M)
  • Appoint 2 individuals to database design, start to think about database
  • Appoint 2 individuals to user interface design, start to think about UI design
  • Individual’s reading

Week 4 Weekends
  • Submit Project schedule, SRS, use-case diagram
  • Combine, refine A&M system specifications
  • 2 people start on database draft design
  • 2 people start on user interface draft design
  • Individual’s reading

Week 5 Wednesday (Lab2)
  • Finalize Analyze and model system specifications
  • Prototyping frontend
  • Prototyping backend

Week 5 Weekends
  • Progress check, reschedule if necessary
  • Submit Analyze and model system specifications
  • Prototyping frontend
  • Prototyping backend

Week 6 Wednesday
  • Progress check, reschedule if necessary
  • Review system requirement
  • Prototyping frontend.
  • Prototyping backend.
  • Form frontend development team
  • Form backend development team
  • Detailed frontend UI design
  • Detailed backend logical design

Week 6 Weekends
  • Progress check, reschedule if necessary
  • Review system requirement
  • Finalize Prototyping frontend.
  • Finalize Prototyping backend.
  • Integrate Detailed frontend UI design to prototype
  • Integrate Detailed backend logical design to prototype
  • Implement major functionalities

Week 7 Wednesday (Lab 3)
  • Progress check, reschedule if necessary
  • Review system requirement
  • Implement major functionalities

Week 8 (CIDP)
  • Daily progress check, reschedule if necessary
  • Fully implement system.
  • Review system requirement when necessary

Week 9 Wednesday (Lab 4)
  • Progress check, reschedule if necessary
  • Finalize implementation
  • Integrate frontend and backend

Week 9 Weekends
  • Finalize project
  • Self project evaluation  

Week 11 Wednesday (Lab 5)
  • Demo and evaluation
 [+]

Thursday, January 28, 2010

A Message to My Dear Teammates

Dear All,

It is a great honor to working with all of you on the same team. Most of us have seen each other, but never worked side by side before. I am looking forward to working with you.

I think CIDP is one of the very few unique opportunities which allow us to think out of academic boundaries and work on the idea which has a real practical value. I wish our CIDP project may last beyond this academic year and it may change the world one day.

“Regretful” is the word I would use if I have not done anything truly different in my years at university. No matter what the outcome of our CIDP will be, I wish we would continue our project as one team.

Best regards,
Chuxin

[+]

Information on Current Project [28-01-2010]

Project Name: Futurus [Latin futurus "going to be", the etymon of English word ”Future”]
Project Slogan: Futurus, the future of humanitarian movement.
Project Topic: A Volunteer Teachers Network Portal System
Target goal: Universal Educationhttp://www.un.org/millenniumgoals/education.shtml
Objective: Best teaching resources at every corner of the world.
Description:
Not everyone willing to volunteer had the chance.

Not everyone volunteered had the resources.

Here, at Futurus, we share what we have, provide what others need.


[+]

Wednesday, January 27, 2010

creatiNno sTUdio Team Information

Team Name: creatiNno sTUdio
Team Members:

  • Bhavdeep Singh


  • Goh Kah Meng


  • Hua Tran Dung (Stephen)


  • Pavani Gulati


  • Ramkumar Nitish


  • Ritika Jain


  • Li Siyi (Allen)


  • Zhao Chuxin (Kiza)*

*Team Leader

[+]